Navigation

  • Skip to Content
NTNU Home

Campusdevelopment

  • Studies
    • Master's programmes in English
    • For exchange students
    • PhD opportunities
    • All programmes of study
    • Courses
    • Financing
    • Language requirements
    • Application process
    • Academic calendar
    • FAQ
  • Research and innovation
    • NTNU research
    • Research excellence
    • Strategic research areas
    • Innovation resources
    • PhD opportunities
  • Life and housing
    • Student in Trondheim
    • Student in Gjøvik
    • Student in Ålesund
    • For researchers
    • Life and housing
  • About NTNU
    • Contact us
    • Faculties and departments
    • Libraries
    • International researcher support
    • Vacancies
    • About NTNU
    • Maps
  1. Campusdevelopment Projects
  2. Helgasetr
  3. When - Schedules and milestones

Språkvelger

Norsk

Elgesetergate 10 - When- Campus development

×
  • Contact
  • News
  • Projects
    • Campus development in Ålesund
    • Helgasetr
      • Why are we building?
      • Where is Helgasetr
      • How do we work?
      • When - Schedules and milestones
      • Documents Helgasetr
      • What is Helgasetr?
    • NTNU University Museum
    • Unified campus
    • Campus development in Gjøvik
    • Center for Mental Health
  • Process
  • Background information
MENU

When

When

– Schedules and milestones

We are now finished with the refinement phase. We are now awaiting the startup grant from the Government. 

The evaluation phase

15 September 2016: Tenders issued to five pre-qualified suppliers

23 January 2017: Tender deadline for design-and-build contract

April 2017: Contractor is chosen and final cost framework is submitted

Refinement phase

May 2017: Announcement of supplier for design-and-build contract

October 2017: Contract signed with supplier of design-and-build contract

November 2017: Start of refinement phase

October 2017: Funding from the National Budget clarified

March 2018: Solutions have been processed

May 2018: Statsbygg sends their report on phase process of the feasability study to Backe

June 2018: Statsbygg sends the feasability study to the Ministry of Education and Research

The construction phase

2019: Expected construction start

2022: Expected completion

when

NTNU
Studies
  • Master's programmes in English
  • For exchange students
  • PhD opportunities
  • Courses
  • Career development
  • Continuing education
  • Application process
Contact
  • Contact NTNU
  • Employees
  • For alumni
  • Press contacts
  • Researcher support
Discover NTNU
  • Experts
  • Vacancies
  • Pictures from NTNU
  • Innovation resources
  • NTNU in Gjøvik
  • NTNU in Trondheim
  • NTNU in Ålesund
  • Maps
About NTNU
  • NTNU's strategy
  • Research excellence
  • Strategic research areas
  • Organizational chart
  • Libraries
  • About the university
Services
  • For employees
  • For students
  • Blackboard
  • Intranet

Norwegian University of Science and Technology

Use of cookies
Accessibility statement (in Norwegian)
Privacy policy
Editoral responsibility
Sign In